Start Phase 3
Phase 2 traced sanctions through the zero-code wrapper, so there is no common/telemetry.py yet; note that build step 1 writes it. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
This commit is contained in:
co-authored by
Claude Opus 5.5
parent
c06d6be4ce
commit
574d7f4038
@@ -2,9 +2,11 @@
|
||||
|
||||
*Part of `docs/roadmap/` — see [`intro.md`](intro.md) for platform/background context and [`summary.md`](summary.md) for how every phase fits together. Prev: [`phase-2.md`](phase-2.md) · Next: [`phase-4.md`](phase-4.md)*
|
||||
|
||||
**Status:** Not started
|
||||
**Status:** In progress
|
||||
|
||||
**Message:** Depends on Phase 2's `common/telemetry.py` bootstrap existing first.
|
||||
**Message:** Started 2026-10-12. Phase 2 got `sanctions` tracing through zero-code
|
||||
`opentelemetry-instrument`, so no `common/telemetry.py` exists yet. Build step 1
|
||||
writes that bootstrap by hand, in the code, to replace the wrapper.
|
||||
|
||||
**Time-box:** 2–3 evenings. This is the biggest phase and the heart of the task.
|
||||
|
||||
|
||||
@@ -18,7 +18,7 @@ warnings), **Time-box**, **Concepts**, **Resources**, **Build**, **Done when**.
|
||||
| 0b | [`phase-0.md`](phase-0.md) | Done | Base project implemented to green (second agent) | 1–2 evenings | Ledgerline running, list of frustrations |
|
||||
| 1 | [`phase-1.md`](phase-1.md) | Done | Deployment: Compose + Traefik on a server | 1 evening | `https://ledgerline.vione.cloud` |
|
||||
| 2 | [`phase-2.md`](phase-2.md) | Done | Concepts + first trace | 1 evening | One trace in Tempo |
|
||||
| 3 | [`phase-3.md`](phase-3.md) | Not started | Distributed tracing | 2–3 evenings | Connected trace across 7 services incl. the async hop |
|
||||
| 3 | [`phase-3.md`](phase-3.md) | In progress | Distributed tracing | 2–3 evenings | Connected trace across 7 services incl. the async hop |
|
||||
| 4 | [`phase-4.md`](phase-4.md) | Not started | Structured logs | 1–2 evenings | Two-way trace↔log correlation |
|
||||
| 5 | [`phase-5.md`](phase-5.md) | Not started | Metrics | 2 evenings | RED per service, service map, exemplars |
|
||||
| 6 | [`phase-6.md`](phase-6.md) | Not started | Dashboards as code | 2 evenings | `kubectl apply -k k8s/` restores all dashboards |
|
||||
|
||||